Andrews and Hascall Halls Electrical Shutdown June 29 & 30, 2017

By Contributing Writer on June 22, 2017

As part of the New Residence Halls building project, we are relocating the electrical switch-gear that supplies power to Andrews Hall and Hascall Hall.

This work has been scheduled with the Village of Hamilton to occur next Thursday and Friday (6/29/17 and 6/30/17).

All power to these buildings will be shut off from 8:00 a.m. on June 29 until 5:00 p.m. on June 30 to complete the work. This will also affect HVAC and fire alarm systems.

Any perishable items in those buildings should also be removed from refrigerators and freezers, and please power off all sensitive computer equipment.

We appreciate your cooperation and understanding during this electrical shutdown and look forward to any questions or concerns regarding the upcoming work. We hope the advance notification will allow sufficient planning to work around the scheduled shutdown.

Jason Miner
Sr. Project Manager
Planning, Design, and Construction


O’Connor and Ho Science Center Air Conditioning Repairs June 23

By Contributing Writer on June 22, 2017

On Friday, June 23, 2017 from 6:00 a.m. to 10:00 a.m., the air conditioning system to O’Connor and Ho Science Center will be limited. During this time frame, the outside air temperature is predicted to be in the High 60s to low 70s, and the reduced capacity should not cause any discomfort to the areas. The reason for the limited capacity is to make emergent repairs to the New Residence Hall’s chilled water supply piping.

If you have any questions, please contact Facilities Department at 315-228-7130.

Respectfully,
Howard Lewis
Mechanical Trades,Heating Plant and Energy Manager
Facilities Department


Academic Drive closure June 21

By Contributing Writer on June 20, 2017

Due to today’s weather forecast, the scheduled paving of Academic Drive will be moved to 6:00 a.m. tomorrow, Wednesday, June 21. Academic Drive will re-open on Thursday, June 22. Thank for your continued patience and cooperation.


Alumni Hall closures July 7–10 and 14–17

By Contributing Writer on June 16, 2017

Please note that Alumni Hall will be closed twice in July, as part of the first-floor entrances and corridor flooring replacement project taking place from July 7 to August 4, 2017.

The building closures will occur over two consecutive weekends, in order to minimize disruptions to occupants and to comply with egress code requirements. There will be limited access to the project area during the week between those weekends.

Alumni Hall Closure Schedule

Friday, July 7 at 4:00 p.m. through Monday, July 10 at 6:00 a.m.

The entire building must be vacated — NO building access during this time, for asbestos abatement at the entrances.

Monday, July 10 at 6:00 a.m. through Friday, July 14 at 4:00 p.m.

Asbestos abatement work will continue in the elevated first-floor corridor. During this time, the building will remain open except for the abatement areas, first-floor classrooms, and office #112, which will be closed; however, the Longyear offices next to the new handicapped ramp entrance will remain accessible.

Friday, July 14 at 4:00 p.m. through Monday, July 17 at 6:00 a.m.

The entire building must be vacated — NO building access during this time, during treatment of the concrete stairs on the north and south ends.

Your cooperation and understanding during this building enhancement project is very much appreciated.

Please feel free to contact me with any questions at 315-228-7142 or e-mail me at dschirripa@colgate.edu.

Regards,
David Schirripa
Project Manager


Academic Drive Closure June 20–21

By Contributing Writer on June 15, 2017

Please be advised that as a part of our annual campus paving project, Academic Drive will be closed as of 6:00 a.m. on Tuesday, June 20 through 3:00 p.m. on Wednesday, June 21.

Adjacent buildings will remain accessible via pedestrian walkways on the Academic Quad side.

We appreciate cooperation and understanding during this busy construction season.

Many thanks,

Emmett A. House III
Grounds Supervisor


McGregory and La Casa electrical outage extended through June 15

By Contributing Writer on June 14, 2017

Please be advised that the electrical work occurring at McGregory and La Casa (OUS) has encountered a few unforeseen setbacks. Power will NOT be restored at 5PM on June 14, 2017 as scheduled. Power will be restored at 5PM on Thursday, June 15, 2017.

We apologize for the inconvenience and appreciate your cooperation during this busy construction season.

Joseph M. Inman
Project Manager


Gate House and O’Connor Water Shutdown, Tuesday, June 13

By Contributing Writer on June 9, 2017

Please be advised that there will be no water service to Gate House and O’Connor Campus Center beginning at 6:00 a.m. on Tuesday, June 13. Water will be restored at approximately 5:00 p.m.

Please be advised that traffic through this area will be restricted. This shutdown is necessary for the construction of the new residence halls.

We appreciate your patience during this busy construction season. Please don’t hesitate to contact me if you have any questions.

Regards,

Jason Miner
Senior Project Manager


Bryan Complex/Conant House Electrical Outage June 8, 2017

By Contributing Writer on June 1, 2017

As part of the Heating Plant Switch Replacement construction project, we will be moving the electrical switch gear from inside the Heating Plant to a new location on the exterior of the Heating Plant. This work is underway and is scheduled to be completed prior to June 30, 2017.

A portion of this project requires all electrical service to Bryan Complex and Conant House to be shut down from 6:00 a.m. to 8:00 p.m. on June 8, 2017.

I appreciate your cooperation and understanding during this electrical shutdown. Please don’t hesitate to contact me with any questions or concerns.

Thank you,
Robert T. Dwyer
Project Manager


Oak Drive Bridge Repointing and repair June 5–July 14, 2017

By Contributing Writer on June 1, 2017

The Oak Drive bridge re-pointing and repair construction project will be starting on Monday, June 5, 2017. The project is addressing much-needed maintenance and repair to the bridge on Oak Drive adjacent to Oak Drive circle. The construction will address one side of the bridge at a time in order to allow traffic to continue to flow. Safety measures will be in place, including signage and barriers to protect workers. Please obey speed limits and prudent vehicular driving practices for the duration of this project. As always, Campus Safety will be monitoring Oak Drive. This work is scheduled for June 5–July 14, 2017.

I appreciate your cooperation and understanding during this period of time; if you have any questions or concerns, please don’t hesitate to contact me.

Thank you,

Robert T. Dwyer

Project Manager


Summer 2017 Campus Construction Update

By Contributing Writer on May 17, 2017

I am writing to provide an update on construction projects that members of the campus community should be aware of in the coming weeks and months.

Traffic Interruptions

Academic Drive

June 12–July 12, 2017
Academic Drive will be re-routed due to utility installs for the Benton Hall project. The Oak Drive entrance to Academic Drive will be closed, and all traffic will enter and exit Academic Drive from Alumni Drive during this timeframe. Signs will be posted.

Academic Drive/Benton Hall Traffic Pattern June 12-July 12, 2017

Academic Drive/Benton Hall Site Traffic Pattern June 12-July 12, 2017

Lally Lane

July 15–September 15, 2017
Traffic will be restricted between Dana Arts Center and 113 Broad St. as we replace the failing underground steam and condensate line.

Oak Drive Bridge

May 22–July 7, 2017
Masonry repointing and repairs will necessitate flagmen-controlled automobile and pedestrian traffic. Please exercise caution when approaching the bridge.

 

Construction and Renovations

Alumni Hall

June 5–August 18, 2017
Replacement of the flooring in the first-floor corridor will necessitate minor pedestrian routing changes. Off-hours building shutdowns are likely throughout the project.

Andy Kerr Stadium

May 21–June 30, 2017
Andy Kerr Stadium — including the track — will be closed for turf replacement, including revised graphics, on Crown Field.

June 5-August 18, 2017
The Dunlap Stands spectator area will be closed for deck seating waterproofing.

McGregory Hall / LaCasa (OUS) Closure

June 13–14, 2017
These buildings will be closed on June 13 and June 14, 2017. All electrical service, including HVAC, fire alarms, and elevators, will be turned off from 8:00 a.m. through 5:00 p.m., in order to move the electrical switch gear and transformer that supply power to the buildings as part of the Benton Hall construction project.

New Residence Halls

May – June 2017
The construction access road from Hamilton Street to the new residence halls site will be constructed and the perimeter site fencing south of Andrews Hall will be installed. Initial site clearing and grubbing will commence shortly after the proper measures are installed within the site boundaries to limit erosion control during construction.

New Residence Halls Site Temporary Access Road

New Residence Halls Site Temporary Access Road

Stillman Hall

May 25, 2017
This will be the completion date for a major renovation of this residence hall, including all new mechanical, electrical, and plumbing systems; data and communication infrastructure; fire protection; and finishes.

Townhouses

June 5–August 18, 2017
The townhouses will be offline for boilers conversion from oil to gas and painting as needed

Vis Lab

May 23–August 18, 2017
The Ho Tung Visualization Laboratory will be closed for renovations and projection system upgrades.

Wynn Hall

May 1–August 11, 2017
This project includes complete renovation of the second-floor teaching labs, and replacement of HVAC equipment and controls building-wide. The staff in this building have relocated for the duration of the project; contact Carrie McFall, the chemistry and health sciences department assistant, at 315-228-7340 or cmcfall@colgate.edu, with questions about individual locations.

Wynn Hall project logistics

 

Best wishes,
Joe Bello
Director of Planning, Design, and Construction