Annual Steam Shutdown June 2017

By Contributing Writer on May 15, 2017

The Facilities Department will be conducting the annual campus steam shutdown beginning at 8 p.m. on June 4 and ending on June 16. The services that will be affected by the utility outage are heating system, potable hot water, and nutritional equipment supplied by steam.

This shutdown is necessary for our staff to inspect and make repairs as needed to the system for the upcoming academic semesters.

The following schedule shows what buildings will be affected and when:

June 4–11 (Hill Line)

  • Alumni Hall
  • Andrews Hall
  • Bryan Complex
  • Memorial Chapel
  • Curtis Hall
  • Drake Hall
  • East Hall
  • Frank Dining Hall
  • Hascall Hall
  • Stillman Hall
  • West Hall
  • Wynn Hall

June 12–16 (Flat Line)

  • Case Library
  • 113 Broad St.
  • Dana Arts Center
  • JB Colgate Hall
  • Lathrop Hall
  • Lawrence Hall
  • Little Hall
  • McGregory Hall
  • Merrill House
  • Olin Hall
  • Persson Hall
  • Ryan Studio
  • Spear House
  • J.C. Colgate Student Union
  • La Casa
  • Huntington Gym
  • Reid Athletics Center
  • Lineberry Pool
  • Service Building

Howard Lewis
Mechanical Trades, Heating Plant, and Energy Manager

 

 


Leave a comment

Comments: Please make sure you keep your feedback thoughtful, on-topic and respectful. Offensive language, personal attacks, or irrelevant comments may be deleted. Responsibility for comments lies with each individual user, not with Colgate University. Comments will not appear immediately. We appreciate your patience.